How to Reprocess a Dataset with Corrected Control Points

Prev Next

To replace or correct the surveyed control points for a dataset, create a new processing task with the same raw dataset and upload the corrected control point file.

  1. Go to Data Processing > Processing Tasks.

  2. Click Create processing task.

  3. Select the same raw dataset.

  4. In the Alignment & Control point phase, upload the corrected surveyed control point file in .csv or .txt format.

  5. Select the Local reference system or Spatial reference system that matches the control point file.

  6. Configure the processing settings.

  7. Click Continue.

  8. Check the settings in the Review phase.

  9. Click Start Processing.

To exclude individual control points, use View control point configuration to deselect them. See How to exclude some control points from Processing.

Note

Reprocessing creates a new processing task. Each successful task consumes processing units, including the original task and the reprocessing task.